Monday, October 10, 2005

Still Waiting...

The lumber arrived this morning from Economy Lumber. A couple of the 8ft. 2x6s look a bit gnarly (lots of wane), but everything was there. It didn't look like $1000+ of lumber, even with the big 16ft. 4x12. But then I spent a couple of hours moving it from the street into the carport, and it certainly felt like that much lumber. My neighbor Jon offered to help, but I had a good start on it and he was off to an appointment, so I declined.

I've been expecting the inspector to call to let me know a window for the inspection, but hadn't heard anything by lunchtime. And I was reminded this is Columbus Day, so I started wondering if they'd scheduled an inspection for a day no inspectors were working. So I called the city, and found out their computers are down...in the whole building. D'oh! Inspectors are making their rounds as best they can, but without access to their files, well...I may be waiting longer. Hmmph. I'm ready to build some walls!

Wednesday, October 05, 2005

Waiting Game

As expected, I've been keeping busy with a variety of things this week. Monday I cemented the DWV lines together, and did some clean up in the basement.

Yesterday I pressure tested the DWV lines, and as expected there were no problems. I haven't tested it under the full 10' column of water, but there shouldn't be any problems with that...besides bracing the ABS pipe. 10' of water even in a 2" pipe is pretty heavy.

Then it was off to the Red Cross for apheresis, and in the afternoon I went and worked at Camron-Stanford House on the database. What a mess. I'm slowly getting my head around it, but I realized a long time ago that it had about 5X as many fields and forms as needed, and they're not consistently or clearly named.

Today I made a trip to Economy Lumber to order, well, lumber. Lots of different stuff for framing and sheathing the walls, all the way up to a 4"x12", 16 ft. long beam. That'll go across the dining room where the existing wall is, supporting the wall above it and the 5' cantilever section of the loft.

I also made a trip to Home Depot (I'm sure they missed me), and picked up some odds and ends, and some material to work at my friend Cindy's. She's the one who runs Oakland Firefighters Random Acts. And given her bad back, full-time work on Random Acts, and that job thingy, she can't do as much work on her property as she'd like. So I put some of the trim around the replacement windows I'd installed a while back, and did a lot of caulking. The wood shingle siding is in pretty bad shape, so I can imagine working on that at some point in the future, too. Then there's the steps that need finishing, if Cindy decides she wants the railing on both sides, the porch decking that needs repair, the deck in the back that needs building... well, between our house, Cindy's, Habitat for Humanity, and the Mexico Mission trips, I'll have no shortage of construction and home improvement stuff to work on.

Friday, September 30, 2005

New Shoes 2

I've known for a while that I'd need new work boots eventually. I don't know how many years ago I went down to Sears and picked up an inexpensive pair of steel-toe work boots. These boots have been out to Habitat countless times, lots of home-improvement projects here, four Mexico mission trips, and who knows what else.

The treads wore off a long time ago. The toe on one wore through to the steel some time back. They're covered in concrete, caulk, a variety of adhesives, and a lot of plain old dirt.

But the final straw was when I went past wearing off the tread and actually wore through the sole. I noticed it when I stepped on some gravel, and could feel the texture with my foot. Hmm, not a good sign. Then one of the laces broke, and it was past time.

I'd stopped by Sears in Oakland, but they didn't have my size in steel toe. Or at least they couldn't find it. Nice people there, but I don't think they know their store very well. So yesterday I stopped by Sears in Pleasanton since I was in the area for a trip to RLC and lunch with my friends Pete and Jim, and got what I wanted with a minimum of fuss for $34.98 plus tax.

I was going to pick up a pressure valve from my friend Rob at church for the DWV line inspection, but I found out that I can do either 5 lbs. of air pressure or a 10 ft. column of water. The latter is easier to find leaks with (not that I expect any with ABS and its gnarly adhesive), and I have what I need, so I'll do that.

Unfortunately the next available inspection isn't until next Monday, the 10th. Quite a bit longer than the first time, and than what I was planning on. There's other stuff I can do to keep busy, like pre-frame some of the walls, but it'd be nice to have that large space of the floor decking to work on. Oh well. There's more work to be done at Camron-Stanford House, apheresis again on Tuesday, and countless other tasks around the house that need doing. Like cleaning up the construction detritus in the basement. Not too long ago I had a nice work space there. Hmm...maybe I can try rescheduling for an earlier time :-) Or maybe I'll go out to Habitat. I haven't been out to the work site for a while, and I've been meaning to go back out.

Yesterday had some interesting other stuff besides new boots and lunch. When I stopped by RLC, I heard the office manager talking to someone about "blah, blah, fire marshal". Fire marshal? Hmm...as a lot of the sound and video equipment there is at least partly my responsibility, and the sound booth has a mess of cords to catch a fire marshal's eye, I asked what it was about.

No problems in the sound booth (I'd wired some new 4 plug outlets there so we didn't have chains of power strips plugged in to other power strips, a definite no-no), but this fire marshal is a bit more particular than the last. Instead of "no flammable materials" in the furnace room, he wants "no materials", period. As storage at church is pretty limited, there was plenty in there: ladders, folding chairs, tables, shelves with random bits and pieces (need some somewhat worn maps of the Holy Land?), and a large pull-down projection screen. Apparently that was purchased back when they started the contemporary service, and they used it for a while for projecting overheads of lyrics. But it had to be off to the side where nobody could see it easily, so it got taken down and stored. Anyways, I spent the next hour finding new homes for the things stored there, and got stuff cleaned up to what will hopefully be the fire marshal's satisifaction. But know anyone who needs a 10' wide pull-down projection screen?

I don't think the cleanup made any difference to safety, but one thing sure did: I found two extension cords in the janitor's closet that were hazards at best. One had the covering torn at the plug, so just the wires were holding it together. The other had the 3rd prong (the safety ground) broken off. Some people do that because they don't have a 3-prong adapter for a 2-prong outlet, but it creates a major safety hazard. The kind where people end up injured or dead. So I threw out those two cords, and bought a new one at the nearby OSH.

Then last night I went to Rooster's Bar in Alameda to take some pictures of a friend's band. Kautz plays guitar at RLC some Sundays and is a pretty good guy, so I took pictures of the band and will be designing a web site for them. Know anyone who has gigs for a talented heavy metal band? They had a gig after the shoot, but unfortunately they weren't going to be on for a couple of hours. And the bar was charging a $7 cover charge. I was pretty sure I didn't want to sit and listen to hours of heavy metal music, even if the bar does have Lagunitas IPA on tap.

And finally, to keep the people who want more pictures on the blog happy, we have a nice shot of the water supply lines. Kat envisioned it, but I took while she was at work. A nice composition for something otherwise pretty mundane.

Wednesday, September 28, 2005

Drain, Drain, Go Away

Yesterday I made a brief attempt at fixing the last leak, but I decided I was going to have to just redo that fitting and the nearby one. In the afternoon it was off to the Red Cross for apheresis. I watched Ocean's Twelve, the sequel to the remake of the 1960 film, Ocean's Eleven. Not a bad movie, but disappointing after the first one, which did a pretty good job of capturing the essence of the original even if they didn't have the "Rat Pack". I always wonder about movie remakes. If the original was great, why remake it? I know, I know...because they don't have any original ideas anymore. What will they remake next? Casablanca?

I started today by disassembling the problem fittings, which took longer than anticipated because there was some water lurking in the pipes. But I got things apart, prepped the new fittings, sweated things, and voilĂ ! It worked first try. Thanks, Jim. You're a good teacher. But my skills will probably be rusty again by the time I'm ready for working on the plumbing again, so don't go anywhere just yet.

After lunch I worked some more on roughing in the DWV system. I'd drawn out how things were supposed to go, but when you actually get to putting pipes in place, dealing with the proper slope (1/4" per foot), various obstacles like floor joists, water supply lines, and the foundation, it gets to be a lot trickier. Oh, and of course you need to start and end up at all the right points. Since I have the main sewer line out of the addition in a fixed location through the foundation wall, that end has to be exact.

I also needed to figure out how to cut the 4" DWV pipe. It was too big to fit in my chopsaw, and I'm not that accurate with a Sawzall, so I ended up building a miter box big enough to hold the 4" pipe. And then made the cuts I needed with hand saw. A lot slower than the chop saw, but it got the job done.

I got all the runs and changes figured out, but needed to make YAHDR (Yet Another Home Depot Run), which was only partly successful. They were out of 4" connectors to join two pipes together, so I'll have to make a visit someplace else to get one when I'm out tomorrow. But there are drain lines from the shower, sink and toilet now. They just need one more fitting, and gluing together, and I'll be ready for an inspection!

Monday, September 26, 2005

One Drip, One Run, Some Errors

Today I pressure-tested the water supply lines that I finished sweating on Saturday after Jim left. Not surprisingly, there were some leaks. After some cycles of drain the lines, re-sweat the leaky joints, turn on the lines, repeat I began to suspect that there was too much water still in some of the lines because the solder wasn't flowing the way it should. Jim suggested I cut out one of the problem sections and re-do as much as I could off-site, then install it. That worked like a charm, and the cold water supply line is now at pressure -- woohoo! There's still one small leak in the hot water supply line, but I'm confident I can fix that tomorrow.

I also laid out the DWV (drain waste vent) pipes, though I had to make a run down to the local ACE hardware for a couple of fittings (and some more solder for the water supply line fixes I was making). But I should be able to get the plumbing rough-in and floor framing inspected this week, and start moving foward with the floor decking and walls!